Construction Activity & Schedule

Project Milestone Schedule

Project Milestone Schedule

Project Milestone Schedule

  • Phase 1 projected completion: August 27, 2025
  • Phase 2 projected completion: October 22, 2025
  • Phase 3 projected completion: December 12, 2025
  • Phase 4 projected completion: February 10, 2026
  • Phase 5 projected completion: May 7, 2026

Two-month Look Ahead

Project Milestone Schedule

Project Milestone Schedule

  • Structural wood framing through Summer 2025.
  • Exterior siding to be installed through Spring 2026.
  • Sitework (sidewalk/paving) ongoing through Spring 2026.
  • Interior MEP rough-in to be completed winter 2025.
  • Interior unit finishes to begin March 2025.

Progress Photos

Contact Us

Drop us a line!

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Project Team

Copyright © 2025 266 Canal Street Construction - All Rights Reserved.

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept